By Ashish Kumar Mishra
When it comes to successfully executing a capital project, the project schedule holds utmost importance, much like how P&IDs solidify a project's scope. Scheduling is not just about meeting timelines; it plays a crucial role in cost management, change management, resource management, and planning. For a project to run smoothly, schedule accuracy and compliance are essential. The project control group is responsible for maintaining schedules, but it should be a team effort. Every team member should understand how their role fits into the schedule and how their tasks impact other team members and project functions.
In the realm of capital project scheduling, Gantt charts are predominantly utilized in industrial environments, with Nirmalya ERP embedded with Project management emerging as the prevailing scheduling platform. The primary goal of the Gantt chart is to pinpoint the critical path of the project through the allocation of project activities. Uncovering the most effective critical path often results in improved project outcomes in terms of both time and cost efficiency.
The most effective project schedules are not hastily put together after receiving an award notice. Instead, they should be carefully planned well in advance of project execution. The scheduling efforts of the execution team should be aligned with how the project estimate was developed. It is actually considered best practice to create the schedule before the estimate is finalized to ensure that accurate durations are incorporated into the cost estimates for labor, field materials (such as scaffolding), and indirect costs (such as supervision and project trailers). Therefore, by the Execution Phase (beginning of Detail Design) of the project, a detailed schedule outlining the sequence of activities should be established. According to the AACE, a detailed schedule is classified as a Class 1 schedule, with schedule definition improving as the project progresses from Class 5 to Class 1.
To begin creating the project schedule, the first step is to establish a Work Breakdown Structure (WBS) for the project. The WBS serves as a visual tool to organize the project work by breaking it down into hierarchical categories, leading to the identification of deliverables and activities within each category, known as Work Packages. This structure does not include time or dependencies in its hierarchy. WBS is represented by the headings of each section and the corresponding activities. It is important to note that the WBS elements are typically arranged similarly in the code of accounts to ensure consistency between cost reports and WBS category budgets. When time durations and dependencies are incorporated into activities, the outcome is a fully developed project schedule.
To create a well-organized project execution schedule for capital projects, follow these steps:
During project execution, the project schedule serves as the primary management tool to ensure alignment with planned expectations. Regular updates should be made to reflect the "earned value" at set intervals, typically daily or weekly, in order to monitor progress relative to initial projections. It is crucial for the project schedule to remain accurate and promptly updated for effective project control. Control processes must be established and rigorously upheld for field quantities, engineering activities, and subcontractor progress to accurately reflect project status in the schedule and progress trackers.
Nirmalya 's Enterprise Resource Planning platform curated for Capital Project streamlines the scheduling process for capital projects, allowing for more efficient completion. This comprehensive platform offers end-to-end project management, complete with detailed execution schedules to reduce project risks and enhance overall project success. Utilizing AI and BI, Nirmalya ERP helps enterprises accelerate projects through analytics and proactive risk management strategies. To learn more about how companies like yours are benefiting from Nirmalya Enterprise Resource Planning, please reach out to us today.